Conditional use authorization

Conditional use authorization is a discretionary approval. The Planning Commission is not checking boxes, it is making findings, and it can say no to a project that satisfies every numerical standard in the code. That is the part operators underestimate.

Deciding body
SF Planning Commission
Typical range
5 to 10 months
Public notice
311 foot mailed notice
Appeal window
30 days to the Board of Supervisors

Our work has been covered by

  • SF Chronicle
  • Mission Local
  • Hoodline
  • SFist
  • Tablehopper
  • SF Business Times
See the coverage

Which uses need it depends on the zoning district, and San Francisco has dozens of them. Article 7 of the Planning Code sets separate rules for each neighborhood commercial district, so a bar that is principally permitted on one commercial corridor requires a hearing six blocks away. The first question is never what you want to open. It is what the district at that address allows.

01

Reading the district before you read the lease

Article 7 districts each carry their own use table, and the differences are not cosmetic. Some corridors cap how much frontage a single use may occupy. Some restrict a second floor use, or require ground floor retail activity. Some have formula retail controls that turn an eleventh location into a conditional use even where the use itself is permitted.

We pull the district controls for the exact address, identify every trigger the project hits, and tell you whether this is a one hearing project, a three approval project, or a site you should walk away from. That answer is worth more early than late.

02

The findings the Commission has to make

Section 303 of the Planning Code sets the criteria. The Commission has to find that the use is necessary or desirable, that it will not be injurious to the neighborhood, that the site is suited to it, and that it complies with the General Plan and the Priority Policies.

Those are the sentences your package has to earn. A real application answers them with specifics: the hours, the occupancy, the sound mitigation, the trash and delivery plan, the staffing, the security approach, and the record of who in the neighborhood was consulted and what changed as a result. A thin package is what turns a continuance into a denial.

03

Notification, outreach and the hearing

Notice goes out by mail to property owners and occupants within 300 feet, a sign goes up on the premises, and the item is published. From the moment that notice lands, the project belongs to the neighborhood as much as to you.

We do outreach before notice, not after. That means merchant associations, the neighborhood organizations that actually show up to hearings, immediate neighbors, and the district supervisor's office. The goal is for the loudest voices at the microphone to be people who already know what you are building. At the hearing we prepare your testimony, handle the presentation, and negotiate conditions language in real time, because conditions written at the table are conditions you have to operate under for years.

04

Conditions, appeals and what comes after

Approval almost always arrives with conditions. Hours of operation, sound limits, security staffing, a good neighbor policy, sometimes a requirement to return to the Commission after a review period. We read those for operability, because a condition that looks reasonable in a hearing room can make a business plan impossible.

A Commission decision can be appealed to the Board of Supervisors within 30 days. We tell clients plainly when an appeal is a real risk on their corridor, so the buildout schedule is not built on an assumption that the 30 days will pass quietly.

Related work

Questions

Conditional Use questions we get

How long does conditional use authorization take in San Francisco?

Five to ten months is the honest range for a project that is complete when it is filed. Intake and review take time before a hearing date is even assigned, and a continuance adds a month or more. Projects that arrive incomplete, or that meet organized opposition, run longer.

Do I need conditional use for a restaurant in San Francisco?

It depends on the zoning district and sometimes on the specific use, the size, and the frontage. In some neighborhood commercial districts a restaurant is principally permitted and needs no hearing. In others it is conditional. We check the district controls for the address rather than generalizing, because generalizing is how projects discover a hearing requirement after the lease is signed.

What makes the Planning Commission deny a conditional use?

In our experience it is rarely the use itself. It is an incomplete record, unaddressed neighborhood opposition, a site that genuinely does not suit the intensity being proposed, or an applicant who has not thought through sound, hours and trash. Most of that is fixable before the hearing, which is the entire argument for starting outreach early.

Can I do buildout while the conditional use is pending?

Work that does not depend on the entitlement can sometimes proceed, but spending on a buildout that only makes sense if the authorization is granted is a real risk. We sequence buildout against the entitlement calendar, and we push for lease terms that do not have you paying full rent through a hearing cycle.

Next step

Not sure which approval your project needs?

Tell us the address and the concept. We will tell you what it takes, in writing, before you spend anything.